The transport of strategic industrial cargo totaling 30,000 FRT from the Port of Samsun to the construction site in Yahşihan, Kırıkkale, has been successfully completed.

Along the approximately 293-kilometer route, a safe and controlled transport operation was carried out using a flyover (bridge bypass) system specifically designed for road and passage conditions for oversized loads weighing up to 410 metric tons.

The operation involved 200 axles, with a total of 820 axle movements. The entire operation, including the assembly and positioning processes using gantry cranes at the construction site, was completed with zero damage.

Contact
Çabamisnak | Kırıkkale CCPP Project
Project Location Yahşihan, Kırıkkale / Turkey
Total Business Volume 30,000 FRT
Heaviest Load Ever Transported 410 metric tons (12.42 m long / 5.42 m wide)
Total Transport Distance 293 Kilometers
Total Axle Travel 200-Axis and 820-Axis Motion

Key Features of the Project

Project-Specific Flyover System
Gantry Crane Installation on Site
Harsh Weather Conditions
SPMT and Hydraulic Axle Management
Engineering and Custom Manufacturing

Gallery

Çabamisnak | Kırıkkale CCPP Project
Çabamisnak | Kırıkkale CCPP Project
Çabamisnak | Kırıkkale CCPP Project
Çabamisnak | Kırıkkale CCPP Project
Çabamisnak | Kırıkkale CCPP Project

On the Site Come on..