South Yoloten Gas Field Development Project

SCROLL DOWN

The road transport portion of a massive logistics operation in the Yoloten region of Turkmenistan, with a record volume of 700,000 FRT, has been successfully completed.

As part of the project, 290 pieces of oversized heavy cargo were transported to the construction site after transit customs clearance procedures were completed at the Turkmenbashi Port.

In the operation, which utilized a total of 270 hydraulic axles and involved 2,068 axle movements, all infrastructure work was completed with zero damage, and the delivery was successfully carried out.

Contact
Çabamisnak | South Yoloten Gas Field Development Project
Project Location Mary, Yoloten / Turkmenistan
Total Business Volume 700,000 FRT
Number of Oversized Shipments 290 Heavy and Oversized (OOG) Loads
Total Axle Travel 270 Hydraulic Axles and 2,068 Axle Movements

Key Features of the Project

Port Operations
High-Volume Industrial Shipping
Harsh Weather Conditions
Hydraulic Axle and Fleet Management
Secure Delivery

Gallery

Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project
Çabamisnak | South Yoloten Gas Field Development Project

On the Site Come on..